When I update actual work in Project baseline updates, why?

C

CJ

I have a detailed project laid out, complete with assigned human resourse
assignments, and saved the baseline. Now when I attempt to enter the actual
hours worked in the "Task Usage" screen, the assigned value imediately
updates to the same value. No variance results. What gives?
 
J

Joe

Try inserting the field "Baseline Work". That will have the original "work"
you generated since you baselined the plan.
 
J

Jan De Messemaeker

Never seen that.
Actual Work immediately updates Work, but I've never seen it update
BaselineWork
HTH
 