I have a detailed project laid out, complete with assigned human resourse
assignments, and saved the baseline. Now when I attempt to enter the actual
hours worked in the "Task Usage" screen, the assigned value imediately
updates to the same value. No variance results. What gives?
assignments, and saved the baseline. Now when I attempt to enter the actual
hours worked in the "Task Usage" screen, the assigned value imediately
updates to the same value. No variance results. What gives?