N
Neil
To all,
I need some help with a baseline cost problem
I'm using MS PRO 2002
In the taskusage view when setting the baseline for a fixed cost item the
baseline cost will prorate the cost (time phase it over the duration) but yet
the the cost detail veiw shows it at the end of the duration where it should
be. I have set the fixed cost accurual to "end" I have changed the the
default to end on the tools options calculation tab to end. So when I pull
over the baseline cost for Earned value I show a false schedule variance. The
only way I found to correct this is to manually fix the baseline which is not
a good answer some of my projects are quite large and have many items to fix.
Has anybody seen this or know how to fix it
I need some help with a baseline cost problem
I'm using MS PRO 2002
In the taskusage view when setting the baseline for a fixed cost item the
baseline cost will prorate the cost (time phase it over the duration) but yet
the the cost detail veiw shows it at the end of the duration where it should
be. I have set the fixed cost accurual to "end" I have changed the the
default to end on the tools options calculation tab to end. So when I pull
over the baseline cost for Earned value I show a false schedule variance. The
only way I found to correct this is to manually fix the baseline which is not
a good answer some of my projects are quite large and have many items to fix.
Has anybody seen this or know how to fix it