A
AndrewE
I'm using Project to manage several contracts I have - I have prepared Gantt
charts for each.
I want the bars in my Gantt charts to represent the general span of days I
have to do a task, so I enter start date and end date accordingly. For
example, I may have a task called "Research Speakers" that I have two weeks
to undertake, starting June 1 through to June 14. This, of course, generates
a Duration for this task of 14 days
However, I've really only got a budget of 12 hours for this work, and
somehow I'd like this displayed on the chart, to remind myself to not go over
budget. I dont' know exactly when in the 2 weeks that I'll expend the 12
hours, and frankly don't need this displayed. I do the work on the task when
I can, based on committments to other projects. I have learned how to
combine projects using the Window / New View option. Very handy.
Suggestions on how to deal with these "budgeted hours"?
charts for each.
I want the bars in my Gantt charts to represent the general span of days I
have to do a task, so I enter start date and end date accordingly. For
example, I may have a task called "Research Speakers" that I have two weeks
to undertake, starting June 1 through to June 14. This, of course, generates
a Duration for this task of 14 days
However, I've really only got a budget of 12 hours for this work, and
somehow I'd like this displayed on the chart, to remind myself to not go over
budget. I dont' know exactly when in the 2 weeks that I'll expend the 12
hours, and frankly don't need this displayed. I do the work on the task when
I can, based on committments to other projects. I have learned how to
combine projects using the Window / New View option. Very handy.
Suggestions on how to deal with these "budgeted hours"?