D
Dennis
Hello
I want for one recourse a workdag from 10hours. I want to do it so that
i give up 1 day duration but from 8 workhours and 2 hours overtime. For
the overtime i can give up fixt cost at the resource. I cant get it don
to make one day from 10 hours. I made a new callender from 08:00 -
19:00 and link tthe calender to the resource.
Now i see at work 8hours and nothing more?? I want to see by duration 1
day, by work 8hours and by overtime 2hours. Then the costs of the
workhours and the costs of the overtime.
I have all the collumns but the dont have any information.
What do i wrong??
Thanks
I want for one recourse a workdag from 10hours. I want to do it so that
i give up 1 day duration but from 8 workhours and 2 hours overtime. For
the overtime i can give up fixt cost at the resource. I cant get it don
to make one day from 10 hours. I made a new callender from 08:00 -
19:00 and link tthe calender to the resource.
Now i see at work 8hours and nothing more?? I want to see by duration 1
day, by work 8hours and by overtime 2hours. Then the costs of the
workhours and the costs of the overtime.
I have all the collumns but the dont have any information.
What do i wrong??
Thanks