In the Resource Sheet view, double-click the resource and in the dialog you
can enter the Max Units and the date of change, but you have to do it
manually, there is no calendar the takes Max Units. I would recommend
splitting the resource into two and setting up a separate calendar for the
resources that work on Saturdays.