Working calendar changes

T

therealcatman

Is there a way to set a resources working calendar as the following, and how?

Resource 1 m-f 700% sat 400%
 
M

Mike Glen

Hi ,

Welcome to this Microsoft Project newsgroup :)

In the Resource Sheet view, double-click the resource and in the dialog you
can enter the Max Units and the date of change, but you have to do it
manually, there is no calendar the takes Max Units. I would recommend
splitting the resource into two and setting up a separate calendar for the
resources that work on Saturdays.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top