Working Days and Non-Working Days

J

JulieS

Hi Mike,

Try Tools > Change Working Time. Select the column heading for Sunday(first
S) click in the option button that says non-default working time. Repeat
for Saturday (the last S).
You can get both Sunday and Saturday with one go if you click on the column
heading for Sunday and then press and hold your control key and click on the
column heading for Saturday.

I hope this helps. Let us know how you get along.

Julie
 
J

John

Mike said:
How can I defalut non-working days as working-days in Project?

Mike,
Depending on how many of the non-working days you want to be working,
you can use one of two approaches. Either go to Tools/Change Working
TIme and make the necessary modifications, or select a 24 Hours Calendar
for your project.

Hope this helps.
John
Project MVP
 