D
Dougal
I am trying to set up a plan to acurately track drawing resources on a small
In-House project. We currently have three draugtshmen on the books who all
work different numbers of hours each week, as follows: -.
The first draughtsman works 39 hrs per week, 100% of the time on this project,
The second draughtsman works 35 hrs per week, 100% of the time on this
project.
The third draughtsman works 35 hrs per week, 75% of the time on this project.
In an attempt to simplify my plan (in terms of hrs spent adjusting it) I
have entered this into the resource sheet as follows: -
Draughtsmen = 257%
(This figure was determined from the following: -
First man = 100% (based on standard working time being 39 hour's per week)
Second Man = 89.7% (i.e. 35hrs/39hrs x100) (based on standard workign time
being 39 hour's per week)
Third Man = 67.28% (i.e. 35hrs/39hrsx100x75%) (based on standard working
time being 39 hour's week)).
Applying this to my plan which has approximatley 50 seperate tasks in total
with each task being assigned a draugtsman resource of 100% for completion; I
was disheartened to find that, when my plan was resource levelled, it would
only assign 200% of the 257% of the resources available to my project in any
given week?
Why is this, and how can I get project to allow all my resources to work the
full hours available in any given week?
Wrestling MS Project 2003
In-House project. We currently have three draugtshmen on the books who all
work different numbers of hours each week, as follows: -.
The first draughtsman works 39 hrs per week, 100% of the time on this project,
The second draughtsman works 35 hrs per week, 100% of the time on this
project.
The third draughtsman works 35 hrs per week, 75% of the time on this project.
In an attempt to simplify my plan (in terms of hrs spent adjusting it) I
have entered this into the resource sheet as follows: -
Draughtsmen = 257%
(This figure was determined from the following: -
First man = 100% (based on standard working time being 39 hour's per week)
Second Man = 89.7% (i.e. 35hrs/39hrs x100) (based on standard workign time
being 39 hour's per week)
Third Man = 67.28% (i.e. 35hrs/39hrsx100x75%) (based on standard working
time being 39 hour's week)).
Applying this to my plan which has approximatley 50 seperate tasks in total
with each task being assigned a draugtsman resource of 100% for completion; I
was disheartened to find that, when my plan was resource levelled, it would
only assign 200% of the 257% of the resources available to my project in any
given week?
Why is this, and how can I get project to allow all my resources to work the
full hours available in any given week?
Wrestling MS Project 2003