Hello,
Supposed I estimate the effort for task to be 2 day and the resource
completes the task in 1 days, the schedule reports that the resource
has worked 200 units (Task Information->Resource->Units). Is it the
right way of representing what has happened? If someone new reviews
the schedule, she/he would get the impression that the resource in
question has worked 16 hours on that day (whereas the reason why the
person has completed the two days work in one day may be because the
estimate is not correct). How do I differenciate between overtime and
wrong estimates?
Regards,
Ravi
Supposed I estimate the effort for task to be 2 day and the resource
completes the task in 1 days, the schedule reports that the resource
has worked 200 units (Task Information->Resource->Units). Is it the
right way of representing what has happened? If someone new reviews
the schedule, she/he would get the impression that the resource in
question has worked 16 hours on that day (whereas the reason why the
person has completed the two days work in one day may be because the
estimate is not correct). How do I differenciate between overtime and
wrong estimates?
Regards,
Ravi