B
ByronSnow
We are tracking general information about a project in a separate file where
there are no resources and therefore no assignments. When we enter values
into actual work on a task, project is occassionally adding an additional
0.02 hrs to the entry. It is doing it differently on different tasks and is
not included in the summary. Does anyone have insight into this?
Example:
Summary Task 1
Sub Task A
Sub TAsk B
enter 2 hours into actual on sub task A is ok, but not 4 - it makes that 4.02.
enter 4 hours into actual on sub task B is ok, but not 2 - it makes that 2.02.
when both tasks have values with 0.02 extra, Summary Task reads 6.02 total.
thanks in advanced for help
there are no resources and therefore no assignments. When we enter values
into actual work on a task, project is occassionally adding an additional
0.02 hrs to the entry. It is doing it differently on different tasks and is
not included in the summary. Does anyone have insight into this?
Example:
Summary Task 1
Sub Task A
Sub TAsk B
enter 2 hours into actual on sub task A is ok, but not 4 - it makes that 4.02.
enter 4 hours into actual on sub task B is ok, but not 2 - it makes that 2.02.
when both tasks have values with 0.02 extra, Summary Task reads 6.02 total.
thanks in advanced for help