0 Base Numbering

D

dy

My company has a development process that starts with Phase 0. Project
starts numbering tasks with 1. Is there a way to make Project Start
numbering at 0?
 
J

Jim Spiller

Insert the Project Summary Task by selecting Tools-Options-View and clicking
on "Show Project Summary Task". The Project Summary Task is level 0.
 