K
Kay Schulz
Hi
I have several tasks, where I know they take y days.
Each task is done by more than one person.
Sometimes two people work on them 50/50, sometimes
30/70 or even 30/40/30.
How can I handle this in MS-Project?
I have the resources entered as 100% because this
is how they work.
Certainly I can enter two names in the resources
column, but this is not helping to find out which
resources are overloaded etc.
Is there a way to do this?
Thanks
Kay
I have several tasks, where I know they take y days.
Each task is done by more than one person.
Sometimes two people work on them 50/50, sometimes
30/70 or even 30/40/30.
How can I handle this in MS-Project?
I have the resources entered as 100% because this
is how they work.
Certainly I can enter two names in the resources
column, but this is not helping to find out which
resources are overloaded etc.
Is there a way to do this?
Thanks
Kay