StuWolf
Hello
We have a task with a number of assignments on it, all completed. In
reality the task is incomplete by one of the resources so we wish to add in
some remaining work. On doing so, the remaining work is immediately
converted into actual work and the task is retained at 100% complete.
Can anyone offer any explanation for this behaviour?
Thanks
Stuart.