We have a PM who is trying to set a task's remaining work to 0 and to 100%
complete. These are the steps he is performing:
1. setting remaining work to 0
2. republishing the task
3. setting task to 100% complete
4. sync'ing actuals
5. republishing the task
These steps work correctly but when he performs the same steps on a
different section of the project the previous values revert back to their
original values.
Any idea as to why this is happening?
Thank you.