1st level tasks versus resources

J

JR Barriuso

Hi to everybody!

I am working with a projectfile where i have inserted many projects (from
project server) of my company. But now I am getting crazy trying to define a
view, report or whatever, where i can view resources work versus each
project. Not versus each task, but the whole projects.

please heeeeeelppp!

thanks in advance

JR Barriuso (Spain)
 
G

Gérard Ducouret

Hello,
You can do that with the OLAP Cube in the Portfolio Analyser:
Create a view in the Portfolio Analyzer
Admin / Manage Views / Add view

Type : Portfolio Analyzer



Gérard Ducouret
 