F
Frank
Hello,
I am having problems with some of my tasks durations being set to ridiculous
lengths of time. Now I am going to have to explain my wording here, the work
for one task for example is 2hrs, the duration is actually 2hrs aswell,
however, the finish date is set at a year or so after the start date. Even
after one of these tasks reaches 100% it is still not moved to before the
status date.
If i force it behind the status date by putting a must finish on constraint
on it (which i know is bad practice) it will move back but it will still
claim that the start date is a year or so before the status date.
I think it may be a problem with the way I am updating the progress. I
update on a weekly basis where I establish the project status date, then i
only update the %work Complete and then use tracking and update project so
that all uncompleted work is moved to after the status date and re-level.
Has anybody encountered a problem such as this before or can see a problem
with the way I am updating the progress?
Any help would be much appreciated,
Kind Regards,
Frank
I am using microsoft project professional 2007 connected to a server by the
way
I am having problems with some of my tasks durations being set to ridiculous
lengths of time. Now I am going to have to explain my wording here, the work
for one task for example is 2hrs, the duration is actually 2hrs aswell,
however, the finish date is set at a year or so after the start date. Even
after one of these tasks reaches 100% it is still not moved to before the
status date.
If i force it behind the status date by putting a must finish on constraint
on it (which i know is bad practice) it will move back but it will still
claim that the start date is a year or so before the status date.
I think it may be a problem with the way I am updating the progress. I
update on a weekly basis where I establish the project status date, then i
only update the %work Complete and then use tracking and update project so
that all uncompleted work is moved to after the status date and re-level.
Has anybody encountered a problem such as this before or can see a problem
with the way I am updating the progress?
Any help would be much appreciated,
Kind Regards,
Frank
I am using microsoft project professional 2007 connected to a server by the
way