Rich Kooyer
Good Morning!
I have a Project in 2002 where I've set the Work Schedule to 24 hours. I've
also opened the Advanced Tab for the task and made sure it's set to 24 hours.
I then try to change the Start Date for the Task and it defaults to Monday
if I try to start it on Sunday. Trying to set it for Saturday defaults it to
Friday.
I figured that there was nothing else to set on the Task to let it allow me
to start on the weekend but there still seems to be something holding it
back. Any suggestions?
Thanks in Advance to the Community!
Rich Kooyer
I have a Project in 2002 where I've set the Work Schedule to 24 hours. I've
also opened the Advanced Tab for the task and made sure it's set to 24 hours.
I then try to change the Start Date for the Task and it defaults to Monday
if I try to start it on Sunday. Trying to set it for Saturday defaults it to
Friday.
I figured that there was nothing else to set on the Task to let it allow me
to start on the weekend but there still seems to be something holding it
back. Any suggestions?
Thanks in Advance to the Community!