S
Susan
Working with Project 2002, my base calender is set at the standard 8 hours/5
days. I have a resource which run 24 hours/7days. I've set this resource's
working time to 24 hours.
When assigning this resource to a 21 day task, the start and finish dates
have a span of 7 days! Solutions? Thanks.