Please can someone advise?
We're running Project Pro 2002 and Server, and our users are updating
their tasks via PWA.
OK - so we've estimated that a task is going to take 10 hours, but it
actually takes 5. The resource enters 5 hours on the timesheet on PWA
and the PM accepts the update. And of course the plan displays that it
is 50% complete. When the PM changes the % complete to 100% the hours
worked change to 10 hours!
How can we get round this please?
Many thanks
lynne