F
Fei
e.g. I have a task which as planned to start on 22/03/07 with 6 hours or work
by resource Tim. When the project started Tim was unavailable on 22/03/07.
The task was then postponed. However Tim was still unavailable for the task 3
days later. The project manager had to modify the task and the task ended up
be done on 26/03/07 for 7 hours or work done by another resource Chris.
In this case I am able to use actual work, actual start and actual finish to
keep track of the date time and work changes. Is there also a way to keep
track of the resource change? I couldn't find an 'actual resource' column.....
by resource Tim. When the project started Tim was unavailable on 22/03/07.
The task was then postponed. However Tim was still unavailable for the task 3
days later. The project manager had to modify the task and the task ended up
be done on 26/03/07 for 7 hours or work done by another resource Chris.
In this case I am able to use actual work, actual start and actual finish to
keep track of the date time and work changes. Is there also a way to keep
track of the resource change? I couldn't find an 'actual resource' column.....