D
Digman
After I set up a project with links and all, i start filling in progress by
entering % complete. If a task was schedule to start sometime in the future,
(say July 4, 2010) and I enter in 10% complete for that task, the Actually
start automatically goes from NA to July 4, 2010. This is incorrect, the
actual start is today!!! What am i missing???
entering % complete. If a task was schedule to start sometime in the future,
(say July 4, 2010) and I enter in 10% complete for that task, the Actually
start automatically goes from NA to July 4, 2010. This is incorrect, the
actual start is today!!! What am i missing???