I have a task where the resource will not be able to meet the desired finish
date. I want to add an additional resource to help out on this task. The
way I did this is add the resource to the specific task at 25% allocation.
Assuming an 8 hour work day, I will get 2 hours per day from her, which is
what I want. The problem is since this task was already in progress, how I
get the starting time of the extra resource to start on the day I add her to
the resource to the task. I ended up going into the task usage view and
specifically selected the days to add the 2 hours in the “work†field. Is
there a better way to do this? I wanted to just add her to the task and
assign the allocation. The end result accomplished my goal, because I was
able to get the task done on time with the extra help.
date. I want to add an additional resource to help out on this task. The
way I did this is add the resource to the specific task at 25% allocation.
Assuming an 8 hour work day, I will get 2 hours per day from her, which is
what I want. The problem is since this task was already in progress, how I
get the starting time of the extra resource to start on the day I add her to
the resource to the task. I ended up going into the task usage view and
specifically selected the days to add the 2 hours in the “work†field. Is
there a better way to do this? I wanted to just add her to the task and
assign the allocation. The end result accomplished my goal, because I was
able to get the task done on time with the extra help.