I also have a question about this.
This seems like the right thing to do (making the assumption that
equipment
is a work resource) but I've found that MSProject actually doesn't
understand
equipment properly.
For example, I'll enter one of my prototype bays as a resource into
MSProject. It's a limited resource that I have. However, once I do that,
MSProject begins to think that my prototype bays can actually add work
effort
to my projects. So all of a sudden, my tasks magically disappear because
my
inanimate bay somehow completed the work for my engineer.
Is there any way around this? Software, plugin, tool or otherwise? I'm
pretty frustrated, trying to get this to all work smoothly.
Steve House said:
Antonio is correct, equipment is typically entered as a work resource.
Materials resources are either used up over the performance of a task -
fuel
for a bulldozer, for example - or incorporated into the task's
deliverable,
for example paint on a wall.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
Cincy11jr said:
What is the proper way to enter equipment into the resource pool? I
have
it
entered as material, but I keep thinking there is a better way to do
it.
Any
help would be greatly appreciated.
Thanks,
Scott