Adding one more resoure in the same activity

K

karthick

Scenario:
An activity has a start and end dates. It started with one resource and in
the midlle of the activty i would have to add andother resource in that same
activity. How it is to done in the MS project 2003?
thanks in Advance.
 
D

davegb

karthick said:
Scenario:
An activity has a start and end dates. It started with one resource and in
the midlle of the activty i would have to add andother resource in that same
activity. How it is to done in the MS project 2003?
thanks in Advance.

I believe that if you mark it some percent complete, then add the
resource, it should just add the new resource for the remaining
duration.

Hope this helps in your world.
 
M

Mike Glen

Hi karthick,

Welcome to this Microsoft Project newsgroup :)

Try Window/Split and double-click in the lower pane and select Resource
schedule. You can now add a new resource with a Delay to indicate its start
date. You may need to adjust the Work hours to get what you want.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top