I have added a few recurring tasks to the Gantt Chart in Project 98.
They do not show up on the calendar with the non-recurring items. Is
there a way to get these to show up?

Thanks in advance!
Katie
 
J

JulieS

Hi Katie,

I don't have Project 98 available to check, but try this. In the Gantt
chart view, make sure all of the occurrences of the recurring tasks are
visible (expanded). Then switch to the Calendar view.

--
I hope this helps. Let us know how you get along.

Julie