Azer Nazair
Obviously, I am new to MS Project. I've read the books
and all that but can't solve this problem.
When I add a resource name - any word in fact - to a
task, the dates I assigned to that task change; the task
is lengthened considerable from 13 days to 55 days!
Why? I have not defined any resources in the project yet?
Is there a default resource calendar somewhere that is
doing this?
Any and all help is more than appreciated.
TIA!
and all that but can't solve this problem.
When I add a resource name - any word in fact - to a
task, the dates I assigned to that task change; the task
is lengthened considerable from 13 days to 55 days!
Why? I have not defined any resources in the project yet?
Is there a default resource calendar somewhere that is
doing this?
Any and all help is more than appreciated.
TIA!