Adding weeks to my project in MSP 2003

M

Michelle

I've been notified that the project has been extended three additional weeks.
When I add them to the schedule, they end up as subtasks of the preceding
week. How do I fix that?

Thank you,

Michelle
 
M

Mike Glen

Hi Michelle,

Welcome to this Microsoft Project newsgroup :)

Well... I don't know how you add weeks! You either extend the Durations of
tasks or add more tasks. I assume you mean the latter. When you have
entered the new tasks, select them all and click the Outdent button.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
M

Michelle

Hi Mike,

Thank you for the welcome. My manager wants me to list the weeks (Week 1,
Week 2, and so on) in the schedule and then list the tasks as subtasks.
However, when I wanted to add Weeks 14 through 16, they ended up as subtasks
of Week 13. I outdented and it didn't correct it; they are still shown as
subtasks.

Michelle
 
M

Mike Glen

Hi Michelle,

In Project's terminology, as I understand you, the terms "Week 1", etc, are
called summaries. To make a task into a summary, you indent the tasks
underneath it. If you have Tasks indented that are not part of a summary,
then you outdent them. If, therefore you select the task Week 14 and
outdent it, it should not be part of Week 13. Are you saying that you can't
outdent Week 14? What version of Project are you using? Project 2003 has
SP2 which corrected problems with outdenting.

I won't be able to follow this up as I'm on holiday for a week - maybe
someone else can help?

Mike Glen
Project MVP
 
S

Steve House

That's the problem right there. The Project task list isn't designed to be
outlined according to time. It's a WORK breakdown outline broken down
according to deliverable, the thing a group of tasks produces. For example,
if you were building a house your summary tasks might be "Lay Foundation",
"Erect Walls", "Install Roof", etc, where the completed foundation, walls,
and roof are the deliverables. Indented under "Lay Foundation" would be
"Dig Hole", "Build Forms", "Pour Concrete", etc - all the things you have to
do to make a complete foundation - and Project would calculate the schedule
when you should plan to do each one of them. The problem with using Week !,
Week 2, Week 3 as summaries is what would happen if a task runs late and has
to push over from one week into the next? There's nothing that would move
it from its original Week 2 summary to now make it a child of the Week 3
summary other than manually editing the task list. If you organize by
deliverable and what was originally a 12 week project has more work added so
it now will take 16 weeks, when you add the new deliverables and the tasks
required to produce them the schedule will automatically get extended out
however far it takes.

One crucial thing to keep in mind. It sounds like your boss already has
some notion that Task X will occur during Week 6 or whatever. But the dates
for tasks ARE NOT a user input into the project schedule. Rather, they are
the software's OUTPUT at the end of the task outlining and resource
assignment process. You don't tell Project what weeks tasks are scheduled
for ... it tells YOU what weeks you should schedule them for. Put another
way, you don't tell it the schedule, it tells you. Task dates are the
output, not the input.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top