adjust actuals

C

css34

I am a PM with every permission in the book. When I go to the Resources page
and select the adjust actuals link in the left hand pane, it brings me to the
correct page, but all the boxes are read only. How do I update my resources
taks for them through PWA?
 
D

Dale Howard [MVP]

css34 --

I believe that the Adjust Actuals feature assumes you are using the Hours of
work done per day or per week method of tracking progress. Is that the
method you are using to track progress in your organization? Let us know.
 
C

css34

currently I am using the option called:

"Actual work done and work remaining: Resources report the actual work done
and the work remaining to be done on each task"

Thanks
 