On MSP Pro 2003, in a true 'admin' project, I'm looking for a simple way to
set up recurring 1 hour weekly meetings using a fixed duration task, say from
Jan 1 to December 31. I want the work to be automatically 'use it or lose
it', without the Project Manager manually deleting uneeded work. Hopefully,
there is a simple answer I missed.
If I use an MSP recurring task, and if the resource doesn't charge the
planned amount of work (example: work = 2 hours, actual work = 1 hour) , the
resource must remember to zero the remaining work, or MSP will move the
uncompleted work (1 hour) to the next week. I realize this 'push forward' is
part of MSP, but in this case we need to 'user it or lose it'. Granted, if
the resource remembers to zero the horsu remaining, there is no uncompleted
work, but too often they forget.
I find a similar situation with fixed duration tasks.
In either case, it seems the project manager must manually delete the
uneeded work. Is there a better way to handle 'use it or lose it' work?
Thanks.
set up recurring 1 hour weekly meetings using a fixed duration task, say from
Jan 1 to December 31. I want the work to be automatically 'use it or lose
it', without the Project Manager manually deleting uneeded work. Hopefully,
there is a simple answer I missed.
If I use an MSP recurring task, and if the resource doesn't charge the
planned amount of work (example: work = 2 hours, actual work = 1 hour) , the
resource must remember to zero the remaining work, or MSP will move the
uncompleted work (1 hour) to the next week. I realize this 'push forward' is
part of MSP, but in this case we need to 'user it or lose it'. Granted, if
the resource remembers to zero the horsu remaining, there is no uncompleted
work, but too often they forget.
I find a similar situation with fixed duration tasks.
In either case, it seems the project manager must manually delete the
uneeded work. Is there a better way to handle 'use it or lose it' work?
Thanks.