P
PM Training 12
We created an admin project for leave and admin type tasks. We use the
default template settings (fixed duration, 1 day, work=0, and assign
resources at 100%, not effort driven).
When a resource charges time to one of the tasks every week (via Project
Server PWA), MS Project extends the duration of the task from one day to the
extent of time actually charged. This is understandable, but the Project
Manager recieves a warning message each time this happens. The error messages
can be overwhelming.
Is there anything we can do to eliminate these types of messages on specific
projects? Thanks for any ideas.
default template settings (fixed duration, 1 day, work=0, and assign
resources at 100%, not effort driven).
When a resource charges time to one of the tasks every week (via Project
Server PWA), MS Project extends the duration of the task from one day to the
extent of time actually charged. This is understandable, but the Project
Manager recieves a warning message each time this happens. The error messages
can be overwhelming.
Is there anything we can do to eliminate these types of messages on specific
projects? Thanks for any ideas.