Adust Dates macro.

M

M-CL

I'm using MS Project 2000, and I need to call the 'Adjust Dates' macro
from another running macro.
Can someone help me how to do this.

TIA
 
D

davegb

M-CL said:
I'm using MS Project 2000, and I need to call the 'Adjust Dates' macro
from another running macro.
Can someone help me how to do this.

TIA

"Adjust Dates" is not a valid macro name. No spaces allowed in macro
names. I dont' have Project on my machine, but assuming the name is
"Adjust_Dates", do the following. The "Adjust_Dates" macro must be
available to the other macro. If it is, just put in

Call Adjust_Dates

Thats it.
 