S
Steve Scott
I have several 3 month fixed duration task and have spread the work out
across the months using the task usage view. In some cases the work does not
start until the 2nd month. When I assign a resource to the task, it pulls
the work in the 2nd month forward to the 1st month which was showing zero
work.
Is the way around this to always ensure fixed duration tasks have some work
at the beginning of the period ie I should have set the start date to
conincide with month 2?
across the months using the task usage view. In some cases the work does not
start until the 2nd month. When I assign a resource to the task, it pulls
the work in the 2nd month forward to the 1st month which was showing zero
work.
Is the way around this to always ensure fixed duration tasks have some work
at the beginning of the period ie I should have set the start date to
conincide with month 2?