TonyLon
Using Project 2000:
Standard Mon-Fri calendar for project.
Have set resource calendar for one specific resource to allow him to work
Saturdays also.
But when I try to enter task using only that resource to start on a
Saturday, then I get the error message saying that I must move to the next
working day (Monday) or change Saturday to a working day.
But if I do the latter then this alters the working week for all existing
tasks on the project (ie: including those that don't even use this resource)
Any ideas?