Alternative resources

D

Darrel Miller

Is there a way to assign an alternative resource to a task so that if the
first resource has no availability then the second resource will be used.

e.g. If there are no welders left, use a welding supervisor instead.
or
If light duty presses are full use a heavy duty press if one is available.

Thanks,

Darrel Miller
Tavis Software Inc.
 
M

Mike Glen

Hi Darrel,

Welcome to this Microsoft Project newsgroup :)

No, sorry :( There is no automatic way to do this, it is something the PM
must and should do.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 