B
bgriffwork
I have a scenario where I need to lock in Finish dates for a schedule,
regardless of the Actuals that are entered. I've tried constraints, but that
doesn't work in all cases. Is there a way to lock in Finish dates for tasks,
summary tasks, and the project, so that those dates don't change regardless
of Actuals?
regardless of the Actuals that are entered. I've tried constraints, but that
doesn't work in all cases. Is there a way to lock in Finish dates for tasks,
summary tasks, and the project, so that those dates don't change regardless
of Actuals?