It would be helpful to me to have a more meaningful ID with which to link MS
Project tasks when I go to enter them from our team's post it notes on the
wall than Project's ID number. Any suggestions, I hope?
 
J

JulieS

Hi Ed,

In addition to Andrew's suggestion to use the Unique ID, you may also
create your own custom WBS and include a different numbering and/or
letter schema. Choose Project > WBS > Define Code to create the code
mask. Then display the WBS field.

You may also find the WBS Predecessors and WBS Successors field helpful.
You may add those fields through Insert > Column.

--
I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
 