Arranging Tasks in the Calendar view of MSProject

J

Joe C.

I drag the tasks into a different order. Save the project. Exit and return.
The tasks returned to the position before I moved them. I tried adding a
column in the project plan for time, sorted on that column but the calendar
view did not recognize the sort. The only option in the layout dialog is
current sort = ID. I am trying to show recurring meeting (which created
correctly). To get the entire name of the meeting to show I did word wrap
and set the duration at 1 day then only show the name in the bar. So if I
could get the order of the bars to stay where I put them, or better yet sort
and stick then all would be well. Is there any hope?
 