Hi there,
Thank you for taking the time to review my posting and respond.
Unfortunately, I don't think your suggestion answers my question and I don't
think I am going to do what I want with MSProject.
What I want to achieve is this...
1. define a plan with a series of activities [for the purpose of this
example we will use 10].
2. define each activity in MS Project so that it rolls up to the Master.
When all 10 tasks are completed, you are 100% done.
3. Tasks 1, 2 and 3 are more important and when these three tasks are
completed, we will be 75% through the project.
4. Tasks 4, 5, 6, 7, 8, 9 and 10, although important are not Crucial to the
success of the project, but still need to occur and still need to be tracked.
When they are completed, we will have done 25% of what needs to occur on the
project.
If I enter a Work column, I am showing duration.
Jan De Messemaeker said:
Hi,
You can define Work.
Generally this is done by assigning resourcs but it can also be one without.
Simply insert the "Work" column in a task view.
HTH