let say, I have a task with 4 days ( 12/25/06 - 12/28/06 ) as duration. In
normal working day, the resource is paid with the Standard Rate of 30/hr but
if the resource has to work on Public Holiday, the new rate would be 40/hr.
What I'm look for is just to apply the new rate to a particular day, like
12/25/06, could have any way to do it? Actually, I had tried this out by
using cost rate tables methods; but the new rate was applied to all days
within that task.
Thanking in advanced.
let say, I have a task with 4 days ( 12/25/06 - 12/28/06 ) as duration. In
normal working day, the resource is paid with the Standard Rate of 30/hr but
if the resource has to work on Public Holiday, the new rate would be 40/hr.
What I'm look for is just to apply the new rate to a particular day, like
12/25/06, could have any way to do it? Actually, I had tried this out by
using cost rate tables methods; but the new rate was applied to all days
within that task.
Thanking in advanced.