T
TomF
I have read several messages but haven't found an answer that makes sense to
me. I have two kinds of recources. Human and Mechanical. The human
resources are on the normal 8hr per day / 5 day per week calendar. The
mechanical resources are on a 24 hour a day / 7 day per week calendar.
I would like the duration for the mechanical resources to be listed in days
(24 hour) and the duration for the human resources to also be listed in days
(8 hour).
Is this possible? If so, how do I set up MS Project?
Thanks,
Thomas
me. I have two kinds of recources. Human and Mechanical. The human
resources are on the normal 8hr per day / 5 day per week calendar. The
mechanical resources are on a 24 hour a day / 7 day per week calendar.
I would like the duration for the mechanical resources to be listed in days
(24 hour) and the duration for the human resources to also be listed in days
(8 hour).
Is this possible? If so, how do I set up MS Project?
Thanks,
Thomas