Assigned/required resources at a given period

L

Lars Hallin

Hi All,

I have been asked to help out with some replanning of a project, and am
trying to take over a plan made by my successor. One need that the PM has is
to be able to see the number of assigne resources during a certain period in
time, i.e. from the first to the last day of a month.

Any suggestions?

Cheers
Lars
 
M

Mike Glen

Hi Lars,

You might get what you want via FAQ Item: 38. Combined Resource Graph

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
L

Lars Hallin

Mike,

Great stuff, thanks a lot!!

Cheers
Lars

Mike Glen said:
Hi Lars,

You might get what you want via FAQ Item: 38. Combined Resource Graph

FAQs, companion products and other useful Project information can be seen
at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 