Assigning more resource as one

C

Clement

I want to know if is possible to build a structure, like RBS, that
alows the folowing:
when i assign to a task an upper level of resources, automatically
assign all resources from lower levels.
for example:
1 Ms Office
1.1 Ms Word
1.2 Ms Excel
1.3 Ms Access etc.

and to assign to the task "Office installation" just the resource 1 Ms
Office and that to automatically assign 1.1, 1.2, 1.3 etc.

is it possible?
 
J

Jan De Messemaeker

Hi Clemant,

Not standard, no. One could imagine a VBA procedure doing it, but it is not
builtin.
HTH
 