I
info
Is there an easy way to highlight multiple tasks (ie:
4,5,6,7,8,12,33,41...etc.) and then assigned all of these task as
dependant on the completion of a different single task (say task #2)?
These multiple tasks might also have other predecessor tasks already
assigned.
I know you can highlight a group of tasks and then link them, but that
puts them in consecutive order-I am looking to assign the entire
group of tasks to one single predecessor task without having to go to
each individual task. Hope this question makes sense.
Thanks
4,5,6,7,8,12,33,41...etc.) and then assigned all of these task as
dependant on the completion of a different single task (say task #2)?
These multiple tasks might also have other predecessor tasks already
assigned.
I know you can highlight a group of tasks and then link them, but that
puts them in consecutive order-I am looking to assign the entire
group of tasks to one single predecessor task without having to go to
each individual task. Hope this question makes sense.
Thanks