S
Stefan Robert
Hi,
I am working with MS Project and I have some difficulties understanding
how assigning ressources work.
Lets say I have a Task that is of type "Fixed Work".
I assign 16h for the work and 16 hours for the duration of the task.
I have two resources that can give 4 hours a week.
Then, If I used Alt+F10 to assign resources and I select both resources
at 100%, the duration of my task will reduce to 15hours.
However, If I do the same thing but by selecting "Information on the
task" and in the Resource tab I select the same 2 resources for the
task, the duration of the task will shrink to 8 hours (like I expected)
Why is there a difference in using the Assign Resource in the tool menu
and by going to the form giving information on a task?
Thanks
Stefan
I am working with MS Project and I have some difficulties understanding
how assigning ressources work.
Lets say I have a Task that is of type "Fixed Work".
I assign 16h for the work and 16 hours for the duration of the task.
I have two resources that can give 4 hours a week.
Then, If I used Alt+F10 to assign resources and I select both resources
at 100%, the duration of my task will reduce to 15hours.
However, If I do the same thing but by selecting "Information on the
task" and in the Resource tab I select the same 2 resources for the
task, the duration of the task will shrink to 8 hours (like I expected)
Why is there a difference in using the Assign Resource in the tool menu
and by going to the form giving information on a task?
Thanks
Stefan