C
Cindy
One of our PMs came to me saying that she changed the dates on a task but the
resource wasn't getting the change in assignment. I investigated and found
this:
The task is a Fixed Duration task. The duration was originally set at 7
days and work was set at 40 horus. One resource was assigned. Everything
worked fine. The PM increased the duration to 73 days to give the resource
more time to finish it (the work remained the same). The task is now showing
the new finish date, however, when I looked at the assignment information it
still had the original date. The work contour indicator had somehow gotten
set to "countour" (I'm sure the PM didn't set it so I'm not sure how it
happened).
I was able to set the new finish date manually (and then had to reset the
work) and everything is now looking good. I have not been able to find any
information on this problem nor have I been able to recreate it.
Any ideas would be helpful.
Thanks,
resource wasn't getting the change in assignment. I investigated and found
this:
The task is a Fixed Duration task. The duration was originally set at 7
days and work was set at 40 horus. One resource was assigned. Everything
worked fine. The PM increased the duration to 73 days to give the resource
more time to finish it (the work remained the same). The task is now showing
the new finish date, however, when I looked at the assignment information it
still had the original date. The work contour indicator had somehow gotten
set to "countour" (I'm sure the PM didn't set it so I'm not sure how it
happened).
I was able to set the new finish date manually (and then had to reset the
work) and everything is now looking good. I have not been able to find any
information on this problem nor have I been able to recreate it.
Any ideas would be helpful.
Thanks,