J
Jackie
I would be grateful if you could let me know how to best represent the
following situation.
Say you have a bunch of tasks that are not linked to any of the tasks above,
and that by default start on the day you start the project eg 16 April. You
need these task to start further on in the schedule, but you cannot select
the date from the start column otherwise inflexible constraints are
introduced in the schedule. On the other hand I cannot lenghten the task
duration as this would not reflect the task actual duration.
Would you use assignment delay? Or how does MS Project deal with this.
Many thanks in advance.
J
following situation.
Say you have a bunch of tasks that are not linked to any of the tasks above,
and that by default start on the day you start the project eg 16 April. You
need these task to start further on in the schedule, but you cannot select
the date from the start column otherwise inflexible constraints are
introduced in the schedule. On the other hand I cannot lenghten the task
duration as this would not reflect the task actual duration.
Would you use assignment delay? Or how does MS Project deal with this.
Many thanks in advance.
J