C
Chris
I have two projects each with a development and a operations timeframe with a
milestone in the middle.
The development is set start as late as possible
The milestone is set to must start on
The operations is set to start as soon as possible
The goal is to be able to adjust (using the mouse in the gantt chart view)
the milestone forward and backwards in time. This set up works perfectly
when dealing with a single instance of this set of 3 elements.
However, when I have more than one instance of this set and I wish to adjust
both elements. I find that if I adjust one milestone (using the mouse) it
automatically sets the other milestone to the constraint start no earlier
than. This destroys the independance of the two sets. I have turned off the
autolink default. Am I missing something to keep these two sets independent
while having them within the same project?
milestone in the middle.
The development is set start as late as possible
The milestone is set to must start on
The operations is set to start as soon as possible
The goal is to be able to adjust (using the mouse in the gantt chart view)
the milestone forward and backwards in time. This set up works perfectly
when dealing with a single instance of this set of 3 elements.
However, when I have more than one instance of this set and I wish to adjust
both elements. I find that if I adjust one milestone (using the mouse) it
automatically sets the other milestone to the constraint start no earlier
than. This destroys the independance of the two sets. I have turned off the
autolink default. Am I missing something to keep these two sets independent
while having them within the same project?