Automatic Contouring -- Help!!

E

Earl Forrence

My PM's seem to be having a problem with contours that is
perplexing me as well.

They've defined tasks over a year's period that are meant
to simply capture the amount of time that their people
perform Continuing Engineering (CE or bug fixing). Since
the budget calls for about 30% CE for the year, the
resources are simply assigned to the CE task at 30%.

Now, if one of the resources spends more than 30% of their
time, then we see an adjustment in the total percentage of
time allocation for the whole task that is reflective of
the maximm % used.

Now, I DO KNOW that MS-P is designed to do that. I don't
especially like it; but that's NOT my problem.

What we are also seeing -- and what the problem is -- is
that the resource's contour for the task is automatically
changed from flat to front-end loaded (althought the icon
of the resource sheet is the one that indicates "The work
assignment is distributed using an edited contour").

This troublesome & weekly anomoly produces resource
allocations in excess of 100% for that task alone -- with
total draws on the resource often above 300% when a total
consolidated Resource View is analyzed.

That is, the automatically assigned contours in many tasks
in many plans causes the current and next few weeks to
have a total draw of up to 136.63 hours per week on a
single resource.

That's nice for the schedule, but I'd expect you would
agree that it's hardly realistic.

What kind of anomoly am I running into here? Any help for
me and mine??

If nothing else, what I'd like to be able to do is turn
off the automatic changing-of-contour feature once the
plan has been Baselined and Published.

Any hope?

Thanks ... Earl
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top