Andrew Lavinsky
Curious question that I have not seen. I have a user with MPP 2007 who has
tasks that are getting extended for no obvious reason:
A task w/ 2d duration, starting on 7/17, ends on 8/1. I found when I looked
at the Resource Usage view, that the task is contoured. By assigning a
resource, I could then go into the Assignment info box, and change the
contouring to flat, and the problem was resolved.
I note that there are about 20-30 tasks that all have the contoured icon
next to them....yet, none of these tasks have resources assigned to them.
Can a task inherit contouring if it came from a previous plan, and then had
the resource removed?
Is there a quick and easy way to drag something down and change all of the
contoured tasks to non-contoured?
Thks in advance
tasks that are getting extended for no obvious reason:
A task w/ 2d duration, starting on 7/17, ends on 8/1. I found when I looked
at the Resource Usage view, that the task is contoured. By assigning a
resource, I could then go into the Assignment info box, and change the
contouring to flat, and the problem was resolved.
I note that there are about 20-30 tasks that all have the contoured icon
next to them....yet, none of these tasks have resources assigned to them.
Can a task inherit contouring if it came from a previous plan, and then had
the resource removed?
Is there a quick and easy way to drag something down and change all of the
contoured tasks to non-contoured?
Thks in advance