P
peternelson
I had a resource setup with 80% availability. I then assigned the
resource in the GANTT chart. He appears correctly Peter[80%]
I go back into the resource sheet and change is availability to 100%.
The Gantt view does not update.
Is that how it's supposed to work all the time?
Is this a default setting that can be changed?
Thanks
resource in the GANTT chart. He appears correctly Peter[80%]
I go back into the resource sheet and change is availability to 100%.
The Gantt view does not update.
Is that how it's supposed to work all the time?
Is this a default setting that can be changed?
Thanks