Rob
If I have already assigned all the resources to tasks at 100% availability
and then decided that 75% would be better to account for administrative time
and the such, what is the best way to update the project plan with the new
info?
As far as I can tell, I have to go to the resource sheet, update all with
75%, and then manually change all resources in the gantt chart to 75% before
I can try leveling again.
and then decided that 75% would be better to account for administrative time
and the such, what is the best way to update the project plan with the new
info?
As far as I can tell, I have to go to the resource sheet, update all with
75%, and then manually change all resources in the gantt chart to 75% before
I can try leveling again.